Construction of Governmental Mass Housing Residential Project
The project is one of the governmental mass housing developments providing residential units for low-income people. It is located in the new city of Sadra, Shiraz.
The development is divided into two sections comprising 240-unit and 450-unit residential developments, consisting of 23 blocks, each containing 30 apartments distributed over 5 floors. The building type is Residential, and the structural system is Concrete.
The Sadra Governmental Mass Housing Project is a large-scale residential development constructed as part of a government housing program aimed at providing affordable residential units for low-income families. Located in the new city of Sadra, the project comprises 690 residential units distributed across 23 residential blocks, each consisting of five floors with six apartments per floor.
With a total built-up area of 60,500 m², the project was designed and executed using a reinforced concrete structural system, providing durable and efficient residential buildings in accordance with modern construction standards. The development was implemented in two phases, including 240-unit and 450-unit residential sections, creating an integrated housing community.
Executed by Omran Maroon Engineers Co. as the Contractor, the project was completed in compliance with engineering standards, technical specifications, and contractual requirements throughout the 24-month construction period, delivering a high-quality residential complex in support of the national mass housing program.
The execution of the Sadra Governmental Mass Housing Project engaged multidisciplinary engineering, technical, and construction teams throughout the project implementation. The construction of 690 residential units across 23 reinforced concrete residential blocks required the coordinated efforts of specialists in civil engineering, structural construction, architectural works, building services, and site management.
The simultaneous execution of multiple residential buildings demanded efficient workforce planning, continuous technical supervision, and effective coordination between engineering and construction teams to maintain construction quality, productivity, and project schedule. The use of a reinforced concrete structural system and standardized construction methods supported the efficient delivery of a large-scale residential development within the planned timeframe.
As the Contractor, Omran Maroon Engineers Co. managed and coordinated all construction activities, ensuring effective workforce organization and the successful execution of the project in full compliance with technical specifications and contractual requirements throughout the 24-month construction period.
Omran Maroon Engineers Co. manages the procurement and supply of construction materials, equipment, and site resources through an integrated supply chain management system. Procurement activities are carried out in accordance with project schedules, technical specifications, and quality requirements, ensuring the timely availability of materials and equipment while supporting efficient project execution.